Filter
3.4
Part 3.4 Termite risk managementPart 3.4 Termite risk management
3.4.1
Requirements for termite management systems
2019: 3.1.4.2
3.4.1
Requirements for termite management systems
2019: 3.1.4.2
- a Class 1 or 10 building is constructed in an area where subterranean termites are known to present a potential risk of attack; and
- a primary building element of a Class 1 or 10 building is considered susceptible to termite attack.
- Steel, aluminium or other metals.
- Concrete.
- Masonry.
- Fibre-reinforced cement.
- Timber — naturally termite resistant in accordance with Appendix C of AS 3660.1.
- Timber — preservative treated in accordance with Appendix D of AS 3660.1.
NT 3.4.1 Requirements for termite management systems2019: 3.1.4.2
- Steel, aluminium or other metals.
- Concrete.
- Masonry.
- Fibre-reinforced cement.
- Timber — naturally termite resistant in accordance with Appendix C of AS 3660.1 in areas where Mastotermes darwiniensis are not prevalent.
- Timber — preservative treated in accordance with Appendix D of AS 3660.1.
QLD 3.4.1 Requirements for termite management systems2019: 3.1.4.2
QLD 3.4.1 Requirements for termite management systems2019: 3.1.4.2
- for a non-temporary Class 1 building, a design life of at least 50 years; or
- for other than a non-temporary Class 1 building, a design life of at least 50 years or the specified design life of the building, whichever is the lesser.
QLD 3.4.1 Requirements for termite management systems2019: 3.1.4.2
QLD 3.4.1 Requirements for termite management systems2019: 3.1.4.2
- installed by excavating trenches, treating the exposed trench and backfilling the trench with treated material; and
- covered by a concrete cover strip not less than 50 mm thick and 300 mm wide measured from the external wall of the building.
Explanatory information
- 3.4.1(1): Termites are not considered to be a risk in Tasmania and a lesser risk in parts of Victoria. The appropriate authority may have records of termite activity for each area and may be able to advise on whether termite risk management is needed.
- 3.4.1(2): Where individual primary building elements are susceptible to termite attack and the remainder of the primary building elements are constructed of termite resistant materials, only the susceptible elements need to be provided with a termite management system.
- 3.4.1(2)(c): states that masonry is not subject to termite attack, however termites may gain entry through mortar and other joints.
- Explanatory Figure 3.4.1 provides a flowchart for identifying if a termite management system is required.
3.4.2
Termite management systems
2019: 3.1.4.3
3.4.2
Termite management systems
2019: 3.1.4.3
Where a termite management system is required it must—
- be selected appropriate to QLD Table 3.4.2; and
- comply with—
- AS 3660.1 subject to clauses QLD 3.4.1(4), (5) and (6); or
- have been tested and passed the tests required by Section 5 of AS 3660.3; and
- have a durable notice installed in accordance with 3.4.3; and
- where a chemical termite management system is used, the chemical must be included on the appropriate authority’s pesticides register.
Footing system | Slab edge exposure | Termite shielding | Stainless steel mesh | Graded stone | Chemicals |
---|---|---|---|---|---|
Concrete slab on ground complying with AS 2870: Penetrations and control joints | Not suitable | Not suitable | Component; or full system subject to 3.4.1(4) | Component; or full system subject to 3.4.1(4) | Full system beneath slab subject to 3.4.1(4) and (5) |
Concrete slab on ground complying with AS 2870: Slab perimeter | Suitable subject to 3.4.1(4) | Not suitable | Component; or full system subject to 3.4.1(4) | Component; or full system subject to 3.4.1(4) | Perimeter system subject to 3.4.1(4) and (6) |
Concrete slab on ground not complying with AS 2870: Beneath slab (includes penetrations and control joints) | Not suitable | Not suitable | Full system subject to 3.4.1(4) | Full system subject to 3.4.1(4) | Full system beneath slab subject to 3.4.1(4) and (5) |
Concrete slab on ground not complying with AS 2870: Slab perimeter | Suitable subject to 3.4.1(4) | Not suitable | Full system subject to 3.4.1(4) | Full system subject to 3.4.1(4) | Perimeter system subject to 3.4.1(4) and (6) |
Suspended floors | Not applicable | Suitable subject to 3.4.1(4) | Suitable subject to 3.4.1(4) | Component; or full system subject to 3.4.1(4) | Full system subject to 3.4.1(4) |
Termite management systems
Where a termite management system is required it must—
- be selected appropriate to Table 3.4.2; and
- comply with—
- AS 3660.1; or
- have been tested and passed the tests required by Section 5 of AS 3660.3; and
- have a durable notice installed in accordance with 3.4.3; and
- include additional termite risk management measures in areas where Mastotermes darwiniensis are prevalent; and
- where a chemical termite management system is used—
- the chemical must be included on the appropriate authority’s pesticides register; and
- when used as an external perimeter termite management system for Mastotermes darwiniensis, it is—
- installed by excavating trenches, treating the exposed trench and backfilling the trench with treated material; and
- covered by a concrete strip not less than 50 mm thick and 300 mm wide measured from the external wall of the building.
Explanatory information
3.4.2(b)(i) provides the option of having a chemical termite management system tested to AS 3660.3. In order for the test results to remain valid, the system would then have to be installed as tested.
Termite management systems
Where a termite management system is required it must—
- be selected appropriate to Table 3.4.2; and
- comply with—
- AS 3660.1; or
- have been tested and passed the tests required by Section 5 of AS 3660.3; and
- have a durable notice installed in accordance with 3.4.3; and
- where a chemical termite management system is used, the chemical must be included on the appropriate authority’s pesticides register.
Building element | Termite management system or component options |
---|---|
Concrete slab-on-ground: slab perimeter or external wall perimeter | Slab edge exposure |
Sheet material | |
Granular material | |
Chemical | |
Concrete slab-on-ground: penetrations/control joints/area beneath the slab (see Note) | Sheet material |
Granular material | |
Chemical | |
Suspended floors | Sheet material |
Granular material | |
Chemical | |
Attachments to buildings | Termite management system to the attachment |
Inspection zone between attachment and building |
Table Notes
The entire area beneath the slab must be treated when the slab-on-ground is not designed and constructed in accordance with AS 2870 or AS 3600.
Explanatory information: Validity of test results
3.4.2(b)(ii) provides the option of having a chemical termite management system tested to AS 3660.3. In order for the test results to remain valid, the system would then have to be installed as tested.
Explanatory information: Component
A component of a system as referred to in Table 3.4.2 is one that, when used in combination with other components, will form a ‘full system’.
For example, if a concrete slab is used as a component of a system, it in itself will not provide a complete termite management system. Depending on the construction methods and the site conditions, additional requirements will be necessary for service penetrations through the concrete slab. Each of these are ‘components’, when integrated, will form a ‘full system’.
Explanatory information: Integrity of the termite management system
There are more than 350 species of termites in Australia, about 30 of which achieve economic importance by causing costly damage to building structures. Due to the nature of termites, it is extremely difficult to prevent them gaining access to a building.
In addition to correct installation of a termite management system, its effectiveness will rely on regular maintenance and competent inspection.
Explanatory information: Attachments to buildings
Attachments referred to in Table 3.4.2 include downpipes, service pipes, steps, verandahs, porches, access ramps, carports, trellises, decks, heated water systems, air-conditioners and the like.
3.4.3
Durable notice
2019: 3.1.4.4
3.4.3
Durable notice
2019: 3.1.4.4
A durable notice must be permanently fixed to the building in a prominent location, such as in a meter box or the like, indicating—
- the termite management system used; and
- the date of installation of the system; and
- where a chemical is used, its life expectancy as listed on the appropriate authority’s register label; and
- the installer’s or manufacturer’s recommendations for the scope and frequency of future inspections for termite activity.
Explanatory information: Appropriate authority
For the purpose of the pesticides register, the appropriate authority is the government body responsible for the registration of pesticides. Currently, the Australian Pesticides and Veterinary Medicines Authority (APMVA) coordinates the registration scheme.
Explanatory information: Durable notice
Where a durable notice is required by 3.4.3, it must be fixed to the building in a prominent location advising the building occupants that the system should be inspected and maintained.
The notice should be clearly written, on a material that will not deteriorate or fade over time and be located in or near the electrical meter box or similar location so that it can be easily seen and read by future owners of the building. Additional information may be included if desired by the person placing the notice.