4.1
Part 4.1 Scope and application of Section 4Part 4.1 Scope and application of Section 4
4.1.1
Scope
New for 2022
4.1.1
Scope
New for 2022
This Section sets out the Deemed-to-Satisfy Provisions for footings and slabs.
Explanatory information
This Section specifies the requirements for the excavation and filling for the footing or slab together with the construction of various alternative concrete slab and footing configurations. The slab and footing configurations detailed in this Section are only suitable for the specified soil classifications. The requirements contained in the remainder of this Section are more general and may be applied to all slab and footing construction.
The requirements of this Section are to be read in conjunction with Part 6.2. The Part 6.2 subfloor ventilation requirements apply to the subfloor space of all suspended floors of a building or deck, including but not limited to, timber and steel-framed subfloors and suspended concrete slabs.
4.1.2
Application
New for 2022
4.1.2
Application
New for 2022
The application of this Section is subject to the following:
- The Governing Requirements of NCC 2022 Volume Two.
- Any conditions set out within the following Deemed-to-Satisfy Provisions of NCC Volume Two: H1D4(2), for footings and slabs.
- The State and Territory variations, additions and deletions contained in the Schedules to the ABCB Housing Provisions and NCC Volume Two.
Explanatory information
In NCC 2019, the content of Section 4 of the ABCB Housing Provisions (other than content added in NCC 2022 or later) was contained in the acceptable construction practices for Part 3.2 of NCC 2019 Volume Two.
4.1.3
Explanation of terms
New for 2022
4.1.3
Explanation of terms
New for 2022
Figures 4.1.3a, 4.1.3b and 4.1.3c depict footing and slab members and associated terminology used to describe them in Part 4.2 of the ABCB Housing Provisions.