Filter
How to use the Housing Provisions
This Section is for information only.
1.1 Introduction
The ABCB Housing Provisions contains Deemed-to-Satisfy Provisions that are considered to be acceptable forms of construction that meet the requirements for complying with Parts H1 to H8 of NCC Volume Two (i.e. they comply with the Performance Requirements listed in Parts H1 to H8 of NCC Volume Two).
There is no obligation to adopt any particular option contained in the ABCB Housing Provisions if it is preferred to meet the Performance Requirements some other way.
However, if one of the options described in the ABCB Housing Provisions or elsewhere in the Deemed-to-Satisfy Provisions of NCC Volume Two is not complied with, then the appropriate authority must be satisfied that the Performance Requirements have been met.
1.2 Application
This Housing Provisions must be applied in accordance with each of the following:
- Section A (Governing Requirements) of NCC Volume Two.
- Any conditions on the use of the ABCB Housing Provisions set out within the Deemed-to-Satisfy Provisions of NCC Volume Two where it is referenced.
- The Scope clause at the beginning of each Section of the ABCB Housing Provisions.
1.3 The scope of the ABCB Housing Provisions
In Section H of NCC Volume Two, some Deemed-to-Satisfy Provisions contain more than one compliance pathway. Usually, the first of these pathways will be by reference to a relevant Australian Standard (or similar) and the second will be by reference to a particular Section or Part of the ABCB Housing Provisions. In these cases, use of the ABCB Housing Provisions is one option for complying with the relevant Deemed-to-Satisfy Provision.
Other Deemed-to-Satisfy Provisions contain only one compliance pathway: either a reference to an Australian Standard (or similar), or a reference to a particular Section or Part of the ABCB Housing Provisions. In these cases, the ABCB Housing Provisions may only be used if it is referenced, and must be used if it is the only compliance option for the particular Deemed-to-Satisfy Provision.
If a Deemed-to-Satisfy Provision does not reference the ABCB Housing Provisions, then the ABCB Housing Provisions cannot be used as a compliance pathway for that particular Deemed-to-Satisfy Provision.
The ABCB Housing Provisions only contains content relevant to the Deemed-to-Satisfy Provisions in NCC Volume Two which call it up. Therefore, the ABCB Housing Provisions should not be interpreted as a comprehensive or complete manual for house building.
Section 2 of the ABCB Housing Provisions contains a number of structural design manuals which can be used to design building elements using engineering principles. There is no obligation for the provisions of Section 2 to be used apart from situations where a particular building, building element or component is required to comply with NCC Volume Two and is not within the scope of any other Deemed-to-Satisfy Provisions.
Section 12 contains additional construction requirements that are ancillary to the construction of a building or structure, such as the construction of swimming pools, heating appliances, fireplaces, methods of attaching decks and balconies to external walls or the like. Section 12 also contains special provisions for construction in alpine areas. Earthquake areas are addressed in Section 2 and flood hazard areas are addressed in the ABCB Standard for Construction of Buildings in Flood Hazard Areas, which is referenced directly by H1D10.
Situations where it is necessary for a mixed application of the ABCB Housing Provisions and other documents referenced in the Deemed-to-Satisfy Provisions of NCC Volume Two may be identified by reference to the differing components of the Performance Requirements (see A2G3).
1.4 Suitability of Performance Solutions
The options described in the Deemed-to-Satisfy Provisions are typical examples of national construction methods. They are not the only means available for complying with NCC Volume Two. The performance format of the NCC provides flexibility and allows the use of alternative construction methods to those described in the Deemed-to-Satisfy Provisions.
1.5 The use of maps
Maps have been used throughout NCC Volume Two, including in the ABCB Housing Provisions, to indicate areas where particular requirements apply. These maps are indicative and some variation in conditions will apply, especially on the border of marked areas.
It is recommended that the appropriate authority be consulted and in most cases they should be able to identify what conditions apply in such areas at the early stage of building design.
1.6 Consultation with appropriate authorities
When building in certain locations there may be local conditions or other site constraints that may limit the type of construction that can be used. This is particularly important with buildings that are constructed in areas subject to increased structural loading conditions that may occur due to geographical, topographical or climatic conditions and soil types.
Appropriate authorities have a wide range of experience and information on the geographical and topographical conditions found in their area of responsibility, and should be consulted during the initial design stage.
1.7 Layout of the ABCB Housing Provisions
Although they do not cover every aspect of housing construction, the ABCB Housing Provisions have nonetheless been organised in a manner that follows the logical construction sequence of a building. Table 1.7 outlines some of the more frequently used details and where they are located in the ABCB Housing Provisions or NCC Volume Two.
Stage | Relevant part | Reference(s) |
---|---|---|
Initial design considerations | Earthworks | 3.2 |
Fire Safety | 9 | |
Facilities | 10.4 | |
Room heights | 10.3 | |
Light and ventilation | 10.5, 10.6 | |
Stairway and ramp construction | 11.2 | |
Energy efficiency | 13 | |
Site preparation and drainage | 3.1, 3.3 | |
Footings and slabs | 4 | |
Masonry | 5 | |
Framing | 6 | |
Roof cladding, gutters and downpipes and wall cladding | 7 | |
Gutters and downpipes | 7.4 | |
Glazing | 8 | |
Barriers and handrails | 11.3 | |
Livable housing design | H8 (NCC Volume Two) | |
Construction issues | Wet areas and external waterproofing | 10.2 |
Sound insulation | 10.7 | |
Condensation management | 10.8 | |
Swimming pools | H7D2 (NCC Volume Two) | |
Termite risk management | 3.4 | |
Earth retaining structures | H1D3 (NCC Volume Two) | |
Subfloor ventilation | 6.2 | |
Smoke alarms and evacuation lighting | 9.5 | |
Boilers, pressure vessels, heating appliances, fireplaces, chimneys and flues | 12.4 | |
Special requirements | Earthquake areas | 2 |
Flood hazard areas | H1D10 (NCC Volume Two) | |
Construction in bushfire areas | H7D4 (NCC Volume Two) | |
Construction in alpine areas | 12.2 | |
Attachment of decks and balconies to external walls of buildings | 12.3 | |
High wind areas | 2 | |
Class 10 buildings and structures | Various |
1.8 Interpretation
Throughout the ABCB Housing Provisions, diagrams, explanatory information and cross-volume considerations are included. A1G4 (interpretation) contains information on these elements in the NCC, which is also applicable when they appear in the ABCB Housing Provisions.
1.9 How to use the requirements of each Section/Part
Each Section of the ABCB Housing Provisions is comprised of a scope statement and one or more Parts which contain the technical provisions which must be followed as appropriate to achieve compliance with the relevant Deemed-to-Satisfy Provisions. Generally, a Deemed-to-Satisfy Provision will refer to a specific Part of the ABCB Housing Provisions in order to link the user directly to the relevant technical provisions.
Each Section contains a scope and application Part which sets out the conditions and limitation applicable to the subsequent Parts contained within that Section. Each Part must only be applied in a way that is consistent with its scope.
Sections are numbered with a single numeral (e.g. Section 2 - Structure).
Parts are numbered with two numbers separated by a decimal (e.g. Part 2.2 – Structural provisions).
Clauses within each Part are numbered with three numbers separated by a decimal point (e.g. Clause 2.2.4 – Determination of structural resistance of materials and forms of construction).
Sub-clauses and below are numbered using the system used throughout the NCC.