NCC 2019 Volume Two Amendment 1
Search the National Construction Code editions
Appropriate Performance Requirements
Where an alternative sound insulation system is proposed as a Performance Solution to that described in Part 3.8.6, that proposal must comply with—
Compliance with this acceptable construction practice satisfies Performance Requirement P2.4.6 for sound insulation.
A separating wall between Class 1 buildings, or a wall that separates a Class 1 building from a Class 10a building which is not associated with the Class 1 building must—
have an Rw + Ctr (airborne) not less than 50; and
be of discontinuous construction if it separates a bathroom, sanitary compartment, laundry or kitchen in one Class 1 building from a habitable room (other than a kitchen) in an adjoining Class 1 building (see Figure 3.8.6.1).
For the purposes of (a)(ii), discontinuous construction means a wall system that has two separate leaves and that is not a staggered stud wall, that complies with the following:
The wall has a minimum 20 mm cavity between leaves.
For masonry walls, where wall ties are required to connect leaves, the ties are of the resilient type.
For walls other than masonry, there is no mechanical linkage between leaves except at the periphery.
A wall required to have sound insulation must continue to—
the underside of the roof above; or
a ceiling that provides the sound insulation required for the wall.
Insulation to reduce both airborne and impact noise transmission is required for parts of a wall that are common to adjoining Class 1 buildings but not parts of a wall located in the subfloor.
The Rw + Ctr sound insulation rating required by 3.8.6.2(a)(i) must—
be determined in accordance with AS/NZS ISO 717.1, using results from laboratory measurements; or
comply with Table 3.8.6.1a to Table 3.8.6.1d and the relevant provisions of 3.8.6.4.
Rw is a measure of airborne sound insulation. Ctr is a spectrum adjustment factor that adjusts for low frequency sound levels. Ctr has been chosen in recognition of the problems caused by the high bass frequency outputs of modern home theatre systems and music reproduction equipment used by occupants of Class 1 buildings.
The wall configurations shown in Table 3.8.6.1a to Table 3.8.6.1d are typical examples. Other proprietary methods are available via testing to AS/NZS ISO 717.1 for meeting the Rw + Ctr requirements of 3.8.6.2.
To achieve the appropriate level of sound insulation, walls must be constructed as follows:
Stud wall junction — junctions of sound insulated walls with any perimeter walls and roof cladding must be sealed in accordance with Figure 3.8.6.2.
Masonry — units must be laid with all joints filled solid, except for articulation joints complying with 3.3.5.13, including those between the masonry and any adjoining construction.
Concrete panels — must have joints between panels and any adjoining construction filled solid.
Plasterboard sheeting —
If two layers are required, the second layer joints must not coincide with those of the first layer (see Figure 3.8.6.3).
Joints between sheets including the outer layer or between sheets and any adjoining construction must be taped and filled solid.
Steel framed construction — steel framing and perimeter members must be installed as follows:
Steel framing members must be not less than 0.6 mm thick.
Studs must be not less than 63 mm in depth unless another depth is specified in Table 3.8.6.1a to Table 3.8.6.1d.
All steel members at the perimeter of the wall must be securely fixed to the adjoining structure and the joints must be caulked so that there are no voids between the steel members and the wall.
Timber-framed construction — timber studs and perimeter members must be installed as follows:
Noggings and like members must not bridge between studs supporting different wall leaves.
All timber members at the perimeter of the wall must be securely fixed to the adjoining structure and the joints must be caulked so there are no voids between the timber members and the wall.
Services must not be chased into concrete or masonry separating walls.
If a duct, soil, waste, water supply or storm water pipe is located in a separating wall—
a door or panel providing access to a duct or pipe required to be separated must—
not open into any habitable room, other than a kitchen; and
in any other part must be firmly fixed so as to overlap the frame or rebate of the frame by not less than 10 mm and be constructed of—
wood, plasterboard or blockboard not less than 33 mm thick; or
compressed fibre reinforced cement sheeting not less than 9 mm thick; or
other suitable material with a mass per unit area not less than 24.4 kg/m2; and
in the case of a water supply pipe, it must—
only be installed in discontinuous construction; and
in the case of a water supply pipe that serves one dwelling, not be fixed to the wall leaf on the side of any other dwelling and have a clearance not less than 10 mm to the other wall leaf.
Electrical outlets must be offset from each other—
in masonry walling, not less than 100 mm; and
in timber or steel-framed walling, not less than 300 mm.
Description |
Rw + Ctr (not less than) |
Construction |
Two leaves of 110 mm clay brick masonry with— |
50 |
|
Two leaves of 110 mm clay brick masonry with—
|
50 |
|
Single leaf of 110 mm clay brick masonry with—
|
50 |
|
Single leaf of 90 mm clay brick masonry with—
|
50 |
|
Single leaf of 220 mm brick masonry with 13 mm cement render on each face. |
50 |
|
Description |
Rw+Ctr (not less than) |
Construction |
150 mm thick plain off form concrete. |
50 |
|
200 mm thick concrete panel with one layer of 13 mm plasterboard or 13 mm cement render on each face. |
50 |
|
100 mm thick concrete panel with—
|
50 |
|
125 mm thick concrete panel with—
|
50 |
|
Description |
Rw+Ctr (not less than) |
Construction |
75 mm thick autoclaved aerated concrete wall panel with—
|
50 |
|
75 mm thick autoclaved aerated concrete wall panel with—
|
50 |
|
Two leaves of 75 mm autoclaved aerated concrete wall panel with—
|
50 |
|
Description |
Rw+Ctr (not less than) |
Construction |
Two rows of 90 x 35 mm timber studs or two rows of 64 mm steels studs at 600 mm centres with—
|
50 |
|
Two rows of 64 mm steel studs at 600 mm centres with—
|
50 |
|
State and Territory Variations
In Northern Territory Part 3.8.6 acceptable construction practice is replaced with the following:
Acceptable construction practice
3.8.6.1 Application
Compliance with this Part satisfies Performance Requirement P2.4.6 for sound insulation.
3.8.6.2 Sound insulation requirements
Separating wall — location and penetrations |
Impact sound resistance (as per Table 3.8.6.2 ) |
R w (as per Table 3.8.6.3) |
Type A Between a bathroom, sanitary compartment, laundry or kitchen and a habitable room (other than a kitchen) in an adjoining Class 1 building (dwelling) (see Figure 3.8.6.1). |
Yes |
50 |
Type B In all other cases to those listed as Type A. (See Figure 3.8.6.1) |
No |
45 |
Soil and waste pipes A waste pipe or other penetration that serves or passes through a separating wall between houses—
|
No |
45 |
Soil and waste pipes A waste pipe or other penetration that serves or passes through a separating wall between houses—
|
No |
30 |
Figure 3.8.6.1 Required R w —Plan view |
|
3.8.6.3 General installation requirements for walls
Figure 3.8.6.2 Typical installation of plaster sheets for sound insulation |
|
3.8.6.4 Soil and waste pipes
If a soil or waste pipe passes through a separating wall—
The wall configurations shown in Tables 3.8.6.2 and 3.8.6.3 are typical examples. Other proprietary methods are available for meeting the Rw and sound impact levels required by Table 3.8.6.1.
Wall construction type |
Design diagram — Plan view |
Cavity brickwork |
|
2 leaves 90 mm brick masonry with— |
|
(a) all joints filled solid with mortar; and |
|
(b) an air space not less than 40 mm between the leaves; and |
|
(c) the leaves connected only by ties in accordance with AS& 3700, except '(for piers—isolated or engaged)' is removed from Clause 8.5.1(d) and where Clause 8.5.1 requires design as for unreinforced masonry in accordance with Section 7, the member must also be designed as unreinforced masonry in accordance with Tables 10.3 and 4.1(a)(i)(C) of AS 3700; and (d) wall tie spacing in accordance with details set out in Part 3.3. |
|
Single leaf brickwork |
|
80 mm thick brick masonry with— |
|
(a) each face rendered 13 mm thick; and |
|
(b) 50x12 mm thick timber battens at not more than 610 mm centres fixed to each face but not recessed into the render; and |
|
(c) one layer of 12 mm thick softboard nailed to the battens; and |
|
(d) 6 mm thick medium density hardboard adhesive-fixed to the softboard. |
|
Concrete blockwork |
|
190 mm thick concrete block masonry with— |
|
(a) each face of the blocks fitted with 50x50 mm timber battens, spaced at not more than 610 mm centres, screw-fixed into resilient plugs with rubber inserts; and |
|
(b) the space between the battens completely filled with mineral or glass wool blanket or batts not less than 50 mm thick; and |
|
(c) the outer face of the battens finished with plasterboard not less than 10 mm thick. |
|
Timber-framed walling |
|
70 x 45 mm F5 staggered timber studs at 600 mm centres both sides on 120x35 mm F5 timber plates with— |
|
(a) one layer of 16 mm fire protective grade plasterboard on both faces; and |
|
(b) 50 mm glass fibre batts. |
|
Timber-framed walling |
|
70 x 45 mm F5 timber double studs at 450 – 600 mm centres with an air space not less than 20 mm between studs with two layers of 13 mm fire protective grade plasterboard on both faces. |
|
Steel stud walling |
|
64 mm staggered metal studs (0.75 mm base metal thickness) at 600 mm centres both sides, clipped in 92 mm metal tracks with— |
|
(a) two layers of 13 mm fire protective grade plasterboard to each side; and |
|
(b) 50 mm glasswool cavity batts. |
|
Steel stud walling |
|
64 mm double metal studs (0.75 mm base metal thickness) at 600 mm centres with an air space not less than 20 mm between studs, in separate frames with no mechanical links with— |
|
(a) two layers of 13 mm fire protective grade plasterboard to each side; and |
|
(b) 50 mm glasswool cavity batts. |
Wall construction type |
R w |
Design diagram — Plan view |
Clay brickwork 110 mm thick in one or more leaves and with a mass per unit area of not less than 290 kg/m2. |
45 |
|
Clay brickwork 80 mm thick, pressed brick and rendered 13 mm on one side, the mass per unit area of the unrendered wall being not less than 215 kg/m2. |
45 |
|
Calcium silicate brickwork 90 mm thick calcium silicate brick with one layer of 10 mm fire protective grade plasterboard on each side. |
45 |
|
Calcium silicate brickwork 90 mm thick calcium silicate brick with one layer of 10 mm fire protective plasterboard and one layer of fire protective plasterboard on metal furring channels. |
45 |
|
Concrete blockwork 190 mm solid units (or thicker) Material density 2200 kg/m3 |
45 |
|
Concrete blockwork 110 mm solid units (or thicker) Material density 2200 kg/m3 Material thickness — 83 mm min. 10 mm plasterboard or 12 mm render on each face. |
45 |
|
Concrete wall In-situ concrete — 125 mm thick and with a density of not less than 2200 kg/m3. |
45 |
|
Steel stud walling With 2 layers of 16 mm thick fire-protective grade plasterboard fixed to each face. |
45 |
|
Steel stud walling With 2 layers of 13 mm plasterboard on both sides of 75 mm studs. |
45 |
|
Timber stud walling 70 x 45 mm timber studs at 450 – 600 mm centres with |
49 |
|
(a) one layer of 16 mm fire protective grade plasterboard on one face; and |
||
(b) 50 mm glass fibre batts; and |
||
(c) one layer of 16 mm fire protective grade plasterboard on metal resilient channel. |
||
Timber stud walling 70 x 45 mm timber studs at 450 – 600 mm centres with two layers of 16 mm fire protective grade plasterboard on both sides. |
46 |
|
Ducts or other construction separating soil and waste pipes from units — masonry Not less than 90 mm thick. |
30 |
|
Ducts or other construction separating soil and waste pipes from units — plasterboard 2 layers of plasterboard each 10 mm thick, fixed to timber studs not less than 75x50 mm and spaced at not more than 400 mm centres. |
30 |
|
Ducts or other construction separating soil and waste pipes from units — plasterboard 2 layers of plasterboard each 13 mm thick, one on each side of steel studs not less than 50 mm deep and spaced at not more than 400 mm centres. |
30 |
|
Figure 3.8.6.3 |
Sound insulation between units — Double stud wall configuration |
|